19.Question: For which business scenario, we will
suggest source list and Quota arrangement?
Answer: Source list:
We will suggest the source list in terms of
agreement-based purchasing.
For specific plants, they require material from
only approved vendors, then we will suggest source list as mandatory for
plants.
When there is a requirement to block single
material/single vendor then we can suggest source list to use.
Forecast based MRP planning- Check
Quota arrangement:
When they are using MRP run with multiple
vendors, then its better to go with Quota.
Even in terms of agreement also they can go
with quota arrangement, because there will be lot of savings and dependency
will not there on single vendor.
Mostly, when we are working with multiple
vendors scenario.