17.Question: What is the purpose of MRP indicator in Source
list?
Answer:
MRP- Material requirement planning
If we want MRP run should take their source
automatically then MRP indicator should setup and for schedule lines to be
generated automatically if MRP is set for 2.
By MRP process we can automate the full
procurement, where from PR through MRP with source and PO through background
jobs and this completes the PR-PO process automate.
Ticket:
User raised a ticket for Quote arrangement,
where Quota is not working as maintained.
Resolution:
As we analyzed the query, we see users use to
fix the source list and they use to remove the indicator as per there clients
request, to work Quote we need source list with no fix indicator and MRP
indicates should be 1.